SAWS Holds Brief Monthly Meeting

SAWS Project Manager Dan Coughlin
SAWS Project Manager Dan Coughlin

The Sheridan Area Water Supply Joint Powers Board were provided with a project update on the Big Goose Water Treatment Plant Clearwell Expansion project Wednesday at their monthly meeting. SAWS Project Manager Dan Coughlin.

The clearwell expansion consists of construction of a 1.5 million gallon underground water storage tank at the Big Goose Water Treatment Plant that will connect to the existing clearwell to increase the storage of treated water.

The estimated cost of the project is $2.78 million and it is expected to be completed by mid-summer.

view counter