Greenhouse for Living Awards Contractor Bid

Wright Brothers has been awarded the bid to build the new Green House facility west of Sheridan.
Wright Brothers has been awarded the bid to build the new Green House facility west of Sheridan.

In a news release from Greenhouse Living for Sheridan, a contractor has been approved and a bid accepted to begin work on the new facility. Doug Osborn is tie President of Alternative Elder Living, and tells us about Wright Brothers as the choice for General Contractor.

Wright Brothers' bid was $5,190,781.00, with the time frame for completion being 240 calendar days.

Wright Brothers was the low bidder and had the quickest completion schedule of the seven contractors who submitted bids. Wright Brothers began as a partnership in 1956, incorporated in 1986 with the current owners in Eagle, Idaho and established their Wyoming office in 2007.

As for when construction begins? Today at a meeting, says Osborn.

Osborn says that seeing the project come to fruition after over four years of working on it is very gratifying, and will be great for the community and the elders who will be served.